San Francisco : Architect and Engineer, Inc · leaf 110
being linedwith concrete. Somewhat less than two miles of lining is still to be placed and uponits completion the 150-mile aqueduct willbe ready to deliver water from HetchHetchy reservoir in Yosemite NationalPark by gravity flovv to Crystal Springsreservoir in San Mateo County. The bringing in of… … ^- O SHAUGHNESSY DAM ON TUOLUMNE RIVER IN YOSEMITE NATIONAL PARKThe dam has a total height of 344 feet which will be increased to 430 feet at a cost of $3,500,000.The present dam was completed in 1923 at a cost of $7,000,000. It was obstructed in every possible way byzealous foes, but doggedly…