Architect and engineer (1905)

San Francisco : Architect and Engineer, Inc · leaf 436

An illustration from Architect and engineer, 1905, leaf 436
Precast concrete wall panels are poured on special casting platformsnear their intended erection area—above illustration shows how sitelooked at the start of one four-day push. Speedy erection of precast concrete walls—the large lifting plate,raised by a special crane, picks up panels by means of… … T-V STUDIO . advanced design, is enabling erection in record time.The Austin Company, designers of the building, wereawarded a contract for construction on March 26,working drawings were started April 19, field workbegan May 5, and by October 1 the entire 60,000-square-foot structure is due to be…