e grooves orchannels on toj) of not less than one inch square. The timbers are to bethoroughly tied together, each run of timber is fastened to the other withnails or spikes. The nails in each run to be not less than eighteen inchesapart and staggered is preferable. It is preferable not to nail the… … Mctlwd of Laying Floor After the completion of the timber work, the concrete or asphaltnmwearing surface is put down and thoroughly compacted, so as to fill allthe channels, and to be about two inches deep over the timbers. It isadvisable to coat the surface of the timbers with hot liquid asphalt.…