complish thistask. The piles were finally driven by a 7500 pound steam hammer,assisted, where hard strata was encountered, by a high pressure jetof water, and brought to place at about 105 feet below the street. Thepiles were of Oregon pine, especially selected, and were about 85 feetlong, the… … PLAN OF PILE FOUNDATIONS, P. G. & E. BUILDINGC. H. Snyder, Engineer therefore, necessary and was accomplished by a membrane of roofingfelt, heavily impregnated with an asphaltic compound, extending acrossthe basement floor and up the sides all around and made absolutelywater-tight. Upon this a…