Chicago : Engineering and Contracting Pub. Co. · leaf 705
placed very wetand allowed to stay overnight in the formswhich were painted with crude oil before everysetting. The cost of the pipe making and laying was: Pipe Making: Cost.810 hrs. mixing and placing in forms at 25 cts $202.50 50 hrs. team hauling water at 50 cts 25.00 158 hrs. foreman oiling and… … Fig. 7—View of Outlet for Pipe CrossingUnder Railway. (This gives for 288 ft. of pipe a cost ofpractically $2 per lineal foot.—Editors.)The cost of laying pipe was as follows: 292 hrs. laborers at 25 cts $ 73.00 45 hrs. foreman at 30 cts 13.50 Total $ 86.50 (This gives for 288 ft. a cost for laying…