Chicago : Engineering and Contracting Pub. Co. · leaf 103
o. 4. forms of the concrete cap. As the concretepiles were sheet piles, and driven close to-gether, the head of the pile had to he reducedin size to receive the hood, Fig. 9, of the cast The fill for the roadway is a sand fill, andis pumped from a dredge in Offatts Bayou.This portion of the work is… … Coo/ Eng V Contg Fig. 5—Lay-out of Contractors Plant Buildings and Service Tracks. steel followers. This limited the length of thehood to 6 ins., and the cushioning was limitedto the same length. Inasmuch as no jettingwas permitted, and the driving was done inexceedingly hard red clay, it presented…
Buildings