Inside Out Library · Explore

Handbook of construction plant, its cost and efficiency (1918)

Dana, Richard Turner, 1876-1928 · New York, McGraw-Hill book company, inc., [etc., etc.] · leaf 118

An illustration from Handbook of construction plant, its cost and efficiency, 1918, leaf 118
Fig. 46. 1 foreman at $3.00 $3.00 6 pick and bar men at $1.50 9.00 12 shovelers at $1.50 18.00 1 horse and driver at $3.50 3.50 Vz trackman at $1.50 75 1% dumpmen at $1.50 2.25 Total labor cost per 10 hours $36.50 The earth, which was extremely hard, was undermined andpried down with picks and… … Fig. 47. cars. The whole gang then started the train, which ran downthe 4% grade to the dump by gravity. After bein§ 4^niped,, It CARS 115 was hauled back by one horse. Thirty-three trains or 198 cars,well loaded, per day, was the output. A car was found to containabout 1 cubic yard of earth place…

Contractors' operations · Building

Internet Archive · Library of Congress · Public Domain Mark 1.0. Free to use for anything.

More pictures from Handbook of construction plant, its cost and efficiency

More like this